Renovations

    Welcome to Lake County, Ohio - General Division Courts Renovations

    RENOVATIONS

    REAR ELEVATION, WITH COLORIZED NEW ADDITION AT NORTH END

    CONSTRUCTION COMPLETED APRIL 15, 2005

    The Grand Jury Room / Court of Appeals Courtroom renovation was completed on April 4, 2005.  The contractor completed the work under the contract, subject to the work required by the "punch list."  Further work will be performed by the county Buildings and Grounds department.

    Judge Eugene A. Lucci moved back into his newly-renovated suite (Courtroom D) on February 22, 2004

    Judge Vincent A. Culotta moved into his new lower level courtroom suite (Courtroom A) on October 13, 2004.

    Judge Eugene A. Lucci moved out of his suite (Courtroom D) pending completion of its renovation.  He took up offices in Judge Collins' former suite on September 7, 2004.

    Judge Richard L. Collins Jr. moved into his new first floor courtroom suite (Courtroom C) on September 3, 2004.

    Judge Colleen A. Falkowski (Domestic Relations) moved into her new second floor courtroom suite on February 23, 2004.

    Judge Eugene A. Lucci moved into the second floor courtroom suite (Courtroom D) formerly occupied by Judge Parks, upon his retirement, on February 2, 2004.  The suite has been partially renovated.  Completion is expected in November 2004.

    Judge Paul H. Mitrovich moved into his new first floor courtroom suite (Courtroom B) on November 25, 2003.

    Broke ground on the 17,500 sq. ft. addition on May 28, 2002

    Construction commenced in second floor offices on May 20, 2002

    Construction commenced in first floor courtroom and office suite suite on May 20, 2002

    CONSTRUCTION COMMENCED APRIL 15, 2002


    MAJOR BIDS ON PROJECT

    Bid Awarded by the Lake County Commissioners on June 3, 2004:

    Front steps replacement -- Harry S. Peterson Company -- $222,000.00

    Bid Awarded by the Lake County Commissioners on June 24, 2003:

    Window replacement/restoration -- East-West Construction Company, Inc. -- $528,790.00

    Bids Awarded by the Lake County Commissioners on March 19, 2002:

    Interiors Package -- Lakeland Management Systems, Inc. -- $1,190,000.00

    Bids Awarded by the Lake County Commissioners on February 26, 2002:

    Plumbing Package -- Detrick Industrial Piping Company -- $505,253.00

    Bids Awarded by the Lake County Commissioners on February 26, 2002:

    Demolition Package -- Martin Enterprises -- $276,000.00

    Site Work Package -- Martin Enterprises -- $264,400.00

    Concrete & Masonry Package -- Northern Valley Contractors -- $1,267,500.00

    Steel Package -- Industrial First, Inc. -- $92,000.00

    General Trades/Carpentry Package -- Henle Builders, Inc. -- $1,691,000.00

    Roofing & Waterproofing Package -- Building Technicians Corporation -- $53,600.00

    HVAC Package -- Cleveland Mechanical, Inc. -- $2,035,000.00

    Electrical Package -- VIP Electric Company -- $1,174,800.00

    Fire Protection Package -- MAC Mechanical Corporation -- $168,000.00